ABC Manufacturing Uses a Kanban System for a Component

Question 56

Multiple Choice

ABC Manufacturing uses a Kanban system for a component.The daily demand is 800 units.Each container has a combined waiting and processing time of 0.34 days.If the container size is 50 and efficiency (safety) factor is 9 percent, how many Kanban card sets should be authorized (round up) ?


A) 5 sets
B) 6 sets
C) 7 sets
D) 8 sets