ABC Manufacturing uses a Kanban system for a component.The daily demand is 800 units.Each container has a combined waiting and processing time of 0.34 days.If the container size is 50 and efficiency (safety) factor is 9 percent, how many Kanban card sets should be authorized (round up) ?
A) 5 sets
B) 6 sets
C) 7 sets
D) 8 sets
Correct Answer:
Verified
Q52: In a Kanban system, the numerator
Q53: A manufacturer of automobile engines is
Q54: Discuss the seven major categories of waste
Q55: Which one of the following statements is
Q57: Which one of the following statements is
Q58: Southwest Airlines illustrates the application of "lean
Q59: Hinge Manufacturing Company employs a Kanban
Q60: Which of the following "lean" ideas is
Q61: A company is using Kanban containers.There
Q62: Explain the 5Ss.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents