A Company Is Using a Kanban System with 2 Containers

Question 63

Essay

A company is using a Kanban system with 2 containers, each holding 50 parts, between a downstream (using) and an upstream (producing) work center.The using work center can handle 250 jobs per day.The average elapsed time for the entire cycle is currently .25 days.The company is concerned with the safety factor for the operation and the size of the containers.
a.What is the efficiency rating of the current operation?
b.If the company decides to use only one container, how many parts must it hold?
c.If the safety factor is changed to .12 and there are still 2 containers, how many parts must each container now hold?

Correct Answer:

verifed

Verified

a.blured image = [KC - d(p + w)] / d(p + w) = [(2)(5...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents