A project has three paths.A-B-C has a length of 25 days.A-D-C has a length of 15 days.Finally, A-E-C has a length of 20 days.Which one of the following statements is true?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
Correct Answer:
Verified
Q24: Which of the following is incorrect regarding
Q25: Which of the following is not a
Q26: Which statement is true regarding activities not
Q27: The county government has decided to redo
Q28: Which of the following is not considered
Q30: A type of organization that can result
Q31: Which step in the project management process
Q33: In which stage in the project life
Q34: In which stage in the project life
Q90: The slack for an activity is equal
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents