An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times:
 Activity  Immediate Predecessors  Normal Time weeks)  a. order materials  none 4 b. clear job sites  none 6 c. excavate job sites b10 d. make trenches for conduit b6 e. install conduit d10 f. form and pour foundations c,d8 g. install wire f6h. install lighting standards  g 5 i. install luminaries h4 j. connect to service i3\begin{array} { l c c } \text { Activity } & \text { Immediate Predecessors } & \underline { \text { Normal Time weeks) } } \\\hline \text { a. order materials } & \text { none } & 4 \\ \text { b. clear job sites } & \text { none } & 6 \\ \text { c. excavate job sites } & \mathrm { b } & 10 \\ \text { d. make trenches for conduit } & \mathrm { b } & 6 \\\text { e. install conduit } & \mathrm { d } & 10 \\ \text { f. form and pour foundations } & c , d & 8 \\ \text { g. install wire } & \mathrm { f } & 6 \\ \mathrm { h } \text {. install lighting standards } & \text { g } & 5 \\ \text { i. install luminaries } & \mathrm { h } & 4 \\\text { j. connect to service } & \mathrm { i } & 3 \\\end{array}
a. When does activity d begin?
b. When does activity f end?

Correct Answer:

verifed

Verified

a. Middle third week...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents