A company wants to develop a project using PERT to modify one of their products which has poor sales. They have determined the following activities, precedence relationships and time estimates in days for the project:
a. What is the expected duration for activity a?
b. What is the variance for activity d?
c. How many paths are there in the network?
d. What is the earliest start ES) time for activity e?
e. What is the slack in days for activity b?f. What is the critical path
g. What is the duration of the critical path in days
h. What is the standard deviation of the critical path
i. What is the probability that the project will take longer than 28 weeks to complete?
Correct Answer:
Answered by Quizplus AI
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q52: Explain the stages of the project life
Q58: Data regarding the activities for a
Q61: A company has developed a project
Q62: A company has used PERT for
Q63: You are responsible for managing an
Q64: You are in charge of the
Q81: Describe the four major steps in the
Q83: List at least six principal factors (contributors)
Q94: Explain the purpose of Gantt charts.
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents