Garst Manufacturing is working on two jobs.Cost is accumulated under a job-order costing system,and overhead is applied on the basis of direct labor hours.The company estimated that overhead would be $64,000 and 10,000 direct labor hours would be worked.Both projects were started and completed in the current accounting period.The following transactions were completed during the period: (a) Used $10,000 of direct material on Project I and $6,800 of direct material on Project II.
(b) Labor costs for the two jobs amounted to the following: Project I,$24,000 (2,000 hours) ; Project II,$44,000 (6,000 hours) .
(c) Project II was sold during the period for $120,000.
The ending balance in Work in Process was:


A) $34,000.
B) $0.
C) $46,800.
D) $136,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents