Heavy Eyes Inc.manufactures custom pillows.Five jobs are waiting to be processed using the SPT priority rule.Their processing times are shown in the following table.What is the mean flow time? 
A) 57 days
B) 11.4 days
C) 17 days
D) 5.4 days
E) 27 days
Correct Answer:
Verified
Q21: If using CR as the priority rule,
Q22: Which of the following is a measure
Q23: If your company is concerned with customer
Q24: The jobs listed below have not yet
Q26: The following jobs are waiting to be
Q26: Operation sequencing creates a work center plan
Q29: The following jobs are waiting to be
Q31: The following jobs are waiting to be
Q35: Using the S/RO rule, which of the
Q39: A measure of response time is:
A) makespan
B)