Green Inc.manufactures a variety of wooden desks.Five jobs are waiting to be processed using the LPT priority rule.Their processing times are shown in the following table.What is the makespan? 
A) 66
B) 13.2
C) 27
D) 5.4
E) 2.4
Correct Answer: