Assume that a company takes 10,000 hours to produce 50,000 units of a product.What is the velocity for the company?
A) 1 unit per hour
B) 3.5 units per hour
C) 2 units per hour
D) 5 units per hour
E) 2.5 units per hour
Correct Answer:
Verified