Unique Company Makes Children's Board Games

Question 136

Multiple Choice

Unique Company makes children's board games.One popular game requires the following amounts of time: processing - 2.5 hours; waiting ? 7 hours; moving - 4.5 hours.Which of the following is the manufacturing cycle efficiency (MCE) of Unique Company? (Note: Round answer to two decimal places.)


A) 17.86%
B) 20.00%
C) 100.00%
D) 25.56%
E) 33.60%