Which of the following is a correct EXCEL formula to solve for the net present value of a project.
A) =NPV (k,CF1, CF2,...CFn) +CF0
B) =NPV (k,CF0,CF1, CF2,...CFn)
C) =NPV (CF0,CF1, CF2,...CFn)
D) =NPV (CF1, CF2,...CFn) +CF0
Correct Answer:
Verified