Figure 15-1 The following information relates to Lancashire Manufacturing:
To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
Refer to Figure 15-1. Which area represents the bottleneck operation?
A) finishing
B) casting
C) molding
D) mixing
Correct Answer:
Verified
Q24: Lean manufacturing shares many of the same
Q41: Reducing the time it takes to configure
Q42: The departments or cells which contain all
Q43: To identify value streams using a two-dimensional
Q47: The new product value stream focuses on
A)developing
Q48: The worth of one or more features
Q49: Figure 15-1 The following information relates to
Q50: In a demand-pull system
A)production is triggered by
Q55: The value stream
A)is made up of all
Q58: The processing department can produce one unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents