Solved

The Direct Labor Time Required to Produce the First Sailboat

Question 73

Multiple Choice

The direct labor time required to produce the first sailboat of a particular model was 3000 hours.If the company believes that an 80% learning curve applies to the production of this model sailboat then the direct labor time required to produce the 2nd boat is estimated to be


A) 600 hours.
B) 2,400 hours.
C) 3,600 hours.
D) 4,000 hours.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents