A ______________ breaks down a project into components,subcomponents,activities,and tasks.
A) work breakdown structure (WBS)
B) scope statement
C) responsibility assignment matrix (RAM)
D) organizational breakdown structure (OBS)
Correct Answer:
Verified
Q10: Project scheduling is recognized as the most
Q18: Two key elements of project control are
Q19: Enterprise project management refers to the management
Q26: Project scope involves a set of procedures
Q27: Because the critical path is the shortest
Q28: Microsoft Project is a software package that
Q29: Unlike PERT,CPM incorporates probabilistic time estimates into
Q30: Global projects rarely are concerned with cultural
Q35: The project management process encompasses
A)planning.
B)scheduling.
C)control.
D)All of the
Q51: Which of the following is not used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents