Hillside Homes,Inc.,and Ideal Builders,Inc.,enter into a construction contract that includes six pages of detailed calculations.Later Hillside,whose project manager compiled the figures,discovers that some numbers were multiplied incorrectly,but Ideal refuses to make changes.A court would most likely
A) allow the parties to rescind the contract.
B) award damages to Hillside for the mistakes.
C) award damages to Ideal for the mistakes.
D) enforce the contract without requiring changes.
Correct Answer:
Verified
Q29: Cooper offers to sell Gable his sport
Q39: Roc buys a farm from Steve,who claims
Q49: Business Investment Company and Chic Properties,Inc.,contract for
Q52: Leyte believes an old comic book he
Q53: At an auction,Vigo bids on an object,believing
Q55: Gina induces Hugh to enter into a
Q56: Dom,a salesperson for Excel Autos,promises Fern that
Q57: Jill and Karl contract for the sale
Q58: Ralph offers to sell Sophie,who is seventeen
Q59: In selling paving stones to Yard &
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents