On March 9 of the Current Year,Job 123 Was Completed

Question 82

Multiple Choice

On March 9 of the current year,Job 123 was completed.The job cost sheet showed a total of $4,000 in direct materials and $6,000 in direct labour at a rate of $20 per direct labour hour.Factory overhead is applied at $30 per direct labour hour.Which of the following debits to finished goods inventory records the completion of Job 123?


A) $4,000
B) $9,000
C) $13,000
D) $19,000