Zeta Inc.'s cost of capital is 12% and the risk-free rate is 5%. It plans to invest in a new project. The cash flow projections ($000) for the project are given below. Calculate the difference in the traditional NPV and the certainty equivalent NPV.
A) $9.43
B) $7.59
C) $30.35
D) $20.92
Correct Answer:
Verified