Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the average number of jobs in the system? 
A) 66
B) 13.2
C) 27
D) 5.4
E) 3.38
Correct Answer:
Verified
Q21: If using CR as the priority rule,
Q29: Which of the following is not an
Q34: Green Inc. manufactures a variety of wooden
Q37: What does makespan measure?
A) WIP inventory
B) due-date
Q44: Using the following data, calculate the average
Q45: Job A is due on day 15,
Q52: Which of the following is a measure
Q53: What does "negative lateness" mean?
A) The job
Q55: Which of the following scheduling rules is
Q57: Consider a production line with five stations.