Jackie is the owner and the manager of an auto repair company. In order to be fair to all the customers, Jackie decides to use the FCFS priority rule in job sequencing. Currently, four cars need to be repaired. Assume that the cars arrive in the order listed, that is, A first, then B, then C, then D. The estimated labor times (in days)and promise dates are shown in the following table. Customers usually do not pick up their cars early. Today is day 0.
Based on the FCFS sequence, calculate the following performance measures: (a)makespan, (b)average job flow time, (c)average number of jobs in the system, (d)average job tardiness.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q102: What are the three kinds of constraints
Q108: What is the mean job flow time
Q110: Job A has a flow time of
Q111: Steve's Steak House currently operates 7 days
Q117: Six jobs are to be processed through
Q119: What does the term "floating employees" refer
Q119: The following jobs need to be processed
Q120: Perfect Inc manufactures a variety of wooden
Q125: The time a job spends in the
Q133: Eli Goldratt's approach to continuous improvement is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents