Which of the following is not a benefit of network planning techniques?
A) graphical display of the project, including the relationships and sequence of activities
B) estimate of the expected project length
C) resources are clearly identified
D) identification of activities that are critical to the timely completion of the project
E) identification of the amount of slack associated with individual activities
Correct Answer:
Verified
Q2: Which of the following is not characteristic
Q3: Actions that consume resources and/or time are
Q4: What is a unique, one-time event that
Q5: Which of the following is not characteristic
Q6: _ structure the sequencing of activities.
A) Evaluation
Q7: Which phase in the project life cycle
Q8: The longest connected route through the path
Q9: Which of the following would probably not
Q10: What does AON stand for?
A) action-oriented-network
B) activity-on-network
C)
Q11: Two type of network diagramming notation include:
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents