An approach for getting projects done faster and more consistently at or before the project due date is ____________________.
A) business process reengineering
B) PERT
C) project inversion
D) backcasting
E) the critical chain approach
Correct Answer:
Verified
Q59: There are four activities on the critical
Q60: With probabilistic time estimates, when we calculate
Q61: Who is responsible for the success and
Q62: Removing safety time from the individual activities
Q63: Which of the following is not included
Q65: A feeder buffer protects a _ path
Q66: PERT is credited with reducing the duration
Q67: The termination phase in the project life
Q68: An activity has eight weeks allotted to
Q69: The two kinds of network diagrams are