Which of the following is not characteristic of adding safety time in the critical chain approach?
A) Probability and statistics provide no insights into the adding of safety time.
B) It can be added by basing time estimates on pessimistic experiences.
C) It is added at the end of the critical path.
D) It can be added by having more safety factors added at each level of management.
E) It can be added to offset possible global reductions in project length made by top management
Correct Answer:
Verified
Q74: Precedence relationships structure the sequencing of activities.
Q75: Planning consists of adjusting the concept to
Q76: A project is a unique, one-time event
Q77: Project managers use network planning techniques to
Q78: Which of the following represents a way
Q80: CPM was originally developed to conceive and
Q81: In network diagramming, arrows represent precedence relationships.
Q82: For projects whose activities have probabilistic time
Q83: An approach for getting projects done faster
Q84: The purpose of change control boards is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents