Figure 15-1 The following information relates to Markely Manufacturing:
To produce a unit of product:
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
-
Refer to Figure 15-1.How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
A) 335 minutes
B) 300 minutes
C) 15 minutes
D) none of these
Correct Answer:
Verified
Q3: Figure 15-1 The following information relates to
Q4: Figure 15-1 The following information relates to
Q7: Lean manufacturing shares many of the same
Q11: _ contain all the operations in close
Q12: Identification of a "value stream," pursuit of
Q21: Lean manufacturing benefits of better quality, reduced
Q26: Lean manufacturing is best defined as
A)an operating
Q43: There are two basic types of non-value
Q49: The order fulfillment value stream focuses on
A)developing
Q58: The processing department can produce one unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents