What establishes that point of time in the future inside of which changes to the MPS must be approved by a higher authority?
A) demand time fence
B) supply time fence
C) authorized time fence
D) frozen time fence
E) planning time fence
Correct Answer:
Verified
Q11: What data are added to create an
Q12: What establishes a point of time in
Q13: Demand management includes all but which of
Q14: To evaluate the MPS in terms of
Q15: In MPS terminology, what is another name
Q17: The MPS available-to-promise row shows:
A) how many
Q18: In the "liquid" portion of the MPS,
Q19: The Master Production Schedule is often stated
Q20: Demonstrated capacity is the _ capacity _
Q21: What is the formula for calculating the