Solved

The First Unit of a Product Took 400 Hours to Complete

Question 75

Multiple Choice

The first unit of a product took 400 hours to complete. The firm plans to produce 8 units in the first month and 10 units in the second month. If an 80% learning curve is expected, how many hours will the firm use to work on the product during the second month?


A) 4000.0 hours
B) 2526.0 hours
C) 3886.4 hours
D) 2138.4 hours
E) 1748.0 hours