The following jobs are waiting to be scheduled. Today is day 9. Determine the sequence of jobs by using LCFS as a priority rule.
A) D-C-A-E-B
B) A-B-C-D-E
C) B-E-A-C-D
D) B-E-C-A-D
E) B-E-C-D-A
Correct Answer:
Verified