Which of the following statements is not a valid scheduling principle?
A) Balance the process rather than the flow.
B) Non-bottleneck usage is determined by some other constraint in the system.
C) Usage and activation of a resource are the same.
D) The process batch should be variable.
E) An hour lost at a bottleneck resource is an hour lost forever.
Correct Answer:
Verified
Q62: Only Roses Flower Shop currently operates 7
Q63: A Gantt chart is a basic scheduling
Q64: Jim-O's fast focus restaurant is opening up
Q65: Flow operations are often related to high
Q66: Backward scheduling determines the earliest possible completion
Q68: The process batch should:
A) match the transfer
Q69: The backlog at a work center increases
Q70: Jim-O's fast focus restaurant is opening up
Q71: Forward scheduling sometimes causes inventory buildup if
Q72: Which of the following statements is not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents