Jackie Is the Owner and the Manager of an Auto

Question 117

Essay

Jackie is the owner and the manager of an auto repair company. In order to be fair to all the customers, Jackie decides to use the FCFS priority rule in job sequencing. Currently, four cars need to be repaired. Assume that the cars arrive in the order listed, that is, A first, then B, then C, then D. The estimated labor times (in days) and promise dates are shown in the following table. Customers usually do not pick up their cars early. Today is day 0.
Jackie is the owner and the manager of an auto repair company. In order to be fair to all the customers, Jackie decides to use the FCFS priority rule in job sequencing. Currently, four cars need to be repaired. Assume that the cars arrive in the order listed, that is, A first, then B, then C, then D. The estimated labor times (in days) and promise dates are shown in the following table. Customers usually do not pick up their cars early. Today is day 0.     Based on the FCFS sequence, calculate the following performance measures: (a) makespan, (b) average job flow time, (c) average number of jobs in the system, (d) average job tardiness.
Based on the FCFS sequence, calculate the following performance measures: (a) makespan, (b) average job flow time, (c) average number of jobs in the system, (d) average job tardiness.

Correct Answer:

verifed

Verified

(a) 19 days, (b) 4.7...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents