If a delay in an activity will delay completion of the whole project, the activity ____________________.
A) is on the critical path
B) has slack
C) is costly
D) is a dummy
E) is represented by a node
Correct Answer:
Verified
Q9: Which of the following would probably not
Q10: What does AON stand for?
A) action-oriented-network
B) activity-on-network
C)
Q11: Two type of network diagramming notation include:
A)
Q12: Which of the following is not a
Q13: Which phase in the project life cycle
Q15: Which phase in the project life cycle
Q16: Project managers use network planning techniques to
Q17: Which phase in the project life cycle
Q18: The critical path is the sequential path
Q19: Which phase in the project life cycle