Everett, Inc. budgeted $1,488,000 for total overhead. The standard variable overhead rate was $2 per direct labour hour, or $6 per unit, based on an anticipated activity level of 600,000 direct labour hours. During the year 220,000 units were produced. Fixed overhead costs incurred were $300,000. The variable overhead budget variance was $19,800 unfavourable, and the actual variable overhead rate was $2.10 per direct labour hour.
The variable overhead efficiency variance was:
A) $76,000 U
B) $63,800 U
C) $46,200 F
D) $44,000 F
Correct Answer:
Verified
Q91: Because managers use estimates in calculating overhead
Q92: Everett, Inc. budgeted $1,488,000 for total overhead.
Q93: Everett, Inc. budgeted $1,488,000 for total overhead.
Q94: Fixed overhead costs are not expected to
Q95: Pardee, Inc. completed operations for the
Q97: Everett, Inc. budgeted $1,488,000 for total overhead.
Q98: Overhead efficiency variances:
A) Provide managers with useful
Q99: Dem Mfg. has gathered the following
Q100: Which of the following variances is least
Q101: Standard costs are used to:
A) Allocate support
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents