At the end of 20x1, SWP Corporation prepared its master budget for 20x2. Selected amounts from that budget, along with actual results for 20x2, are presented below: Budgeted Actual
Sales $180,000 $210,000
Research and development cost 25,000 20,000
Interest revenue 7,600 7,000
Cost of goods sold 60,000 65,000
Marketing costs 45,000 45,000
The research and development cost variance could be explained by:
A) Starting too many projects
B) Cost increases due to new information technologies
C) Efficient cost management
D) Higher salaries
Correct Answer:
Verified
Q68: Intentionally understating revenues and / or overstating
Q68: A budget that reflects a range of
Q70: Which of the following is a simple
Q84: At the end of 20x1, SWP Corporation
Q84: The primary disadvantage of zero-based budgeting is:
A)
Q85: In 20x2, OSW Corporation budgeted its sales
Q86: ATR Corporation's budgeted product costs for the
Q91: ATR Corporation's budgeted product costs for the
Q92: At the end of 20x1, SWP Corporation
Q95: When an organization implements activity-based budgeting, managers
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents