Stonebarger Fountains Manufactures Customized Fountains and Uses Two Types of Assembly

Question 166

Essay

Stonebarger Fountains manufactures customized fountains and uses two types of assembly processes. Some parts of the fountains are completely assembled by labour. Other parts, such as the pump mechanisms, are made by machines. The company uses job costing, but has modified the system to reflect the different types of processes that fountains undergo. The following department overhead rates are used for the production plant:
Overhead cost pool Allocation rate
Labour assembly $25 per direct labour hour
Machine assembly $10 per machine hour
Quality testing $30 per testing hour
Resources used for Fountain #35
Direct labour hours 5.0 hours
Machine hours 2.5 hours
Testing hours 2.0 hours
If a single plantwide overhead rate were used instead of separate overhead cost pool rates, overhead would have been allocated to jobs at $56 per direct labour hour.
a)What overhead cost should be allocated to Fountain #35 using the plantwide manufacturing overhead rate?
b)What total overhead cost should be allocated to Fountain #35 using the separate process overhead rates?
c)Why do the allocated amounts in parts (a)and (b)differ?
d)Explain why Stonebarger would use three different overhead allocation bases.
e)Discuss whether increasing the number of overhead cost pools always increases the accuracy of costs allocated to jobs.

Correct Answer:

verifed

Verified

a)$56 x 5 = $280
b)Total costs = $210 (5...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents