Managers at Art's Custom Saddle Manufacturers believe that the learning rate for new employees is about 90%. If it takes a new employee 10 hours to make the first saddle, estimate the cumulative average time per saddle for a new employee to make four saddles. Use the following values as needed to respond:
Ln(95%) / ln(2) = -0.074
Ln(90%) / ln(2) = -0.152
Ln(85%) / ln(2) = -0.234
Ln(80%) / ln(2) = -0.322
Ln(75%) / ln(2) = -0.415
Ln(70%) / ln(2) = -0.515
A) 8) 1 hours per saddle
B) 5) 3 hours per saddle
C) 7) 6 hours per saddle
D) Cannot be determined
Correct Answer:
Verified
Q21: Estimates of future costs can be used
Q37: Jackie's Kennels is located in a small
Q39: Jackie's Kennels is located in a small
Q40: Changes in cost behaviour over time are
Q41: Discretionary costs reflect:
A) The costs that managers
Q43: The cumulative average-time learning curve can be
Q45: Estimating a cost function using past cost
Q47: A firm will build 8 units of
Q48: In most accounting information systems, costs are
Q57: The best source for determining historical costs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents