Assume That a Revised Performance Report Is Prepared for the 11,000-Unit

Question 111

Essay

Assume that a revised performance report is prepared for the 11,000-unit level of production using a flexible budget approach. Compute the cost variances for each of the following. Indicate whether each variance is favorable (F) or unfavorable (U).
a. Direct materials variance from flexible budget: $_____________
b. Direct labor variance from flexible budget: $_____________
c. Total manufacturing overhead variance from flexible budget: $_____________

Correct Answer:

verifed

Verified

a. $4,000 Favorable
...