Which of the following are true regarding activity-based costing?
A) A primary goal of using ABC is the accurate allocation of manufacturing overhead to product lines.
B) Under ABC, direct labor hours is never used to allocate overhead costs to activity pools or product lines.
C) The use of ABC is indicated when it is suspected that each of the firm's product lines consume approximately the same amount of overhead resources but the current allocation scheme assigns each line a substantially different amount.
D) ABC can be used in conjunction with process costing.
Correct Answer:
Verified
Q71: What are the total manufacturing overhead costs
Q82: Under- and over-applied overhead
What is meant by
Q92: Overhead application rate
Define the term cost driver
Q96: Selecting an activity base
Listed below are
Q97: Application of overhead
Pyramid Corporation manufactures a single
Q102: 118.Using ABC to allocate manufacturing overhead can
Q103: When job costing is in use, under-applied
Q104: Which of the following would be the
Q105: 114.Which of the following businesses would most
Q106: What is the finished goods inventory at
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents