In 2010, Indiana incurred costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Using the percentage-of-completion method, Indiana:
A) Recognized $15 million gross profit on the project in 2010.
B) Recognized $13.5 million gross profit on the project in 2010.
C) Recognized $6 million gross profit on the project in 2010.
D) Recognized $1.5 million gross profit on the project in 2010.The project is 70% complete after 2010 (i.e., $94.5 million costs to date/ $135 million estimated total costs) .The estimated gross profit is now $15 million (i.e., $150 million $135 million) , so gross profit to date is $10.5 million (70% $15 million) .$9 million was recognized in 2009, per question 102, so $1.5 million more is recognized in 2010.
Correct Answer:
Verified
Q62: What is the fixed contract price for
Q63: Assume that Steffi paid the $50,000 in
Q64: What are CCC's estimated remaining construction costs
Q65: Assuming BCC uses the percentage-of-completion method of
Q66: What were the construction billings by CCC
Q68: Assume that Steffi signed a $50,000 installment
Q69: Assume that at the time of signing
Q70: Assuming BCC uses the percentage-of-completion method of
Q71: Sullivan should recognize revenue for the two
Q72: EITF 00-21 covers revenue recognition for multiple-part
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents