Question 83

Multiple Choice

On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows:   Dreamworld had $5,000,000 in 12% bonds outstanding through both years. - What was the final cost of Dreamworld's warehouse? A)  $2,154,480. B)  $2,143,860. C)  $1,950,000. D)  $1,254,000. Dreamworld had $5,000,000 in 12% bonds outstanding through both years.
- What was the final cost of Dreamworld's warehouse?


A) $2,154,480.
B) $2,143,860.
C) $1,950,000.
D) $1,254,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents