Latest start time (LS) is the latest time by which a specific activity must be
A) started in order for the entire project to be finished by its required completion time.
B) started in order for the entire project to be started by its required completion time.
C) finished in order for the entire project to be finished by its required completion time.
D) finished in order for the entire project to be started by its required completion time.
Correct Answer:
Verified
Q47: Latest finish time (LF)is the latest time
Q48: Latest start time is calculated by
A) subtracting
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D
Q53: With projects for which there is a
Q54: Earliest finish time (EF)is the earliest time
Q55: Calculate the latest finish for Task B
Q56: Total slack for the project is the
Q57: Calculate the earliest start for Task B
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents