Project prices and budgets should include ____ to pay for additional costs associated with implementing response plans.
A) a padded budget
B) a contingency or management reserve
C) expenses for other charges in the office to help
D) extra overhead
Correct Answer:
Verified
Q33: A risk assessment matrix is a tool
Q34: Risks may change as the project progresses
Q35: _ is a rating of low, medium,
Q36: _ is a rating of low, medium,
Q37: Some level of risk planning should be
Q39: Establishing risk categories may help to identify
Q40: Risks can be identified by using all
Q41: _ is the possibility that an unwarranted
Q42: The most common method of identifying the
Q43: Establishing risk categories may help to identify