Commercial Construction,Inc

Question 38

Multiple Choice

Commercial Construction,Inc.(CCI) ,contracts to build a store for Rita's Pizza Company with Rita's payment due on June 1.On June 1,Rita's bank is closed,and for this reason,Rita's claims it cannot pay on time.In this situation


A) CCI is in breach of contract.
B) Rita's is in breach of contract.
C) the contract is discharged.
D) the contract is suspended.

Correct Answer: