If a project requires coordinating hundreds of activities, some of which must be done simultaneously and some of which cannot begin until earlier activities have been completed, which of the following tools should be used?
A) Gantt chart
B) breakeven analysis
C) load chart
D) PERT network
E) linear programming
Correct Answer:
Verified