Fixed price contracts require the availability of at least one supplier that has the qualifications and performance history that assures the needs of the project can be met.
Correct Answer:
Verified
Q9: In the case of vendors, instead of
Q10: In partnerships, both parties benefit from the
Q11: A request for quote focuses on meeting
Q12: The project team typically develops a description
Q13: Work done by members of the organization
Q15: Cost reimbursable contracts are most often used
Q16: The process of obtaining goods and services
Q17: On smaller projects, a procurement organization is
Q18: Vendors and suppliers usually require payments during
Q19: A cost reimbursable contract with a fixed