On highly complex projects, _____.
A) basic measures such as percentage of activities completed and percentage of budget spent are adequate for budget evaluation
B) the process for evaluating risk is more informal with risk assessment meetings conducted every once in a while to assess risks at different phases of the project
C) an outside expert may be included in the risk assessment process and the risk assessment plan may take a more prominent role in the project execution plan
D) the project management team may develop a list of items perceived to be higher risk and track them during project reviews
E) the project manager may informally track items that may be considered risk items
Correct Answer:
Verified
Q25: Projects with high scores for internal complexity
Q26: Reactive project managers:
A) do not consider risks.
B)
Q27: Which of the following is true about
Q28: Proactive project managers:
A) do not consider risks.
B)
Q29: Inadequacy of resources is an example of
Q31: _ simulation is a statistical model used
Q32: Which of the following is true about
Q33: _ is about developing an understanding of
Q34: An) _ organizes the risks that have
Q35: There is _ correlation between project risk
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents