The most accurate and time-consuming estimating method:
A) uses the statistical relationship that exists between historical data and a particular delineated list of other variables.
B) is to identify the cost of each item in each activity of the schedule, including labor and materials.
C) uses the actual costs from previous projects as a basis for estimating the costs for the current project.
D) involves scaling estimates which are based on other project estimates upward or downward.
E) involves sorting detailed cost estimates by activity and then subtotaling activities to determine the cost for each activity.
Correct Answer:
Verified
Q29: _ is the money held to pay
Q30: Estimate to complete equals budget at completion
Q31: Contractual agreements with vendors can be managed
Q32: Estimates in the earliest stages of project
Q33: In estimating costs to compare and select
Q35: A request for proposal RFP):
A) is used
Q36: If the money needed to pay for
Q37: Which of the following is true about
Q38: Reconsidering the selection of the project should
Q39: If a project consists of activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents