If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount.
Correct Answer:
Verified
Q3: To execute the master schedule, the major
Q4: The difference between the early start date
Q5: The Gantt chart is also called a
Q6: To calculate early start dates, begin with
Q7: An estimate is an educated guess based
Q9: A common resource constraint is availability.
Q10: The master schedule is rarely part of
Q11: Most activities in a network diagram have
Q12: If the float on activities that are
Q13: A project that has completed 25 percent