Which of the following is true about a work breakdown structure WBS) ?
A) Developing a WBS begins by defining and developing lists of all activities needed to accomplish the work of the project.
B) The first draft of the WBS includes activities at the low-level.
C) The first draft of the WBS typically includes the minor activities required to accomplish the deliverables identified in the project scope of work.
D) The WBS is decomposed to the level that the client needs to control the project.
E) Typically, smaller and simpler projects require more detailed WBS.
Correct Answer:
Verified
Q33: To consider the availability of team members,
Q34: The most detailed versions of the schedule
Q35: Which of the following is NOT true
Q36: The unit of time used to develop
Q37: Open Source software is always a better
Q39: The _ schedule is a summary level
Q40: The relationship between a predecessor activity and
Q41: Lead time is _.
A) the amount of
Q42: The time an activity that is not
Q43: An updated schedule that shows the present
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents