Which of the Following Is True About a Work Breakdown

Question 38

Multiple Choice

Which of the following is true about a work breakdown structure WBS) ?


A) Developing a WBS begins by defining and developing lists of all activities needed to accomplish the work of the project.
B) The first draft of the WBS includes activities at the low-level.
C) The first draft of the WBS typically includes the minor activities required to accomplish the deliverables identified in the project scope of work.
D) The WBS is decomposed to the level that the client needs to control the project.
E) Typically, smaller and simpler projects require more detailed WBS.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents