Which of the following is a step in calculating the early start dates of subsequent activities, assuming finish-start relationships?
A) Add the predecessor activity's duration to its finish date.
B) Refer to the resource calendar that applies to the people and equipment necessary for the activity.
C) Add the lead time or subtract the lag time.
D) Deduct the number of off-days that the activity would span on the resource calendars.
E) Assign the calculated date as the early start date of the predecessor activity.
Correct Answer:
Verified
Q51: Activities that have predecessor-successor relationships occur _.
A)
Q52: The _ is the process of determining
Q53: _ the schedule is a term used
Q54: A project can have _, which means
Q55: All of the following are techniques project
Q57: An) _ is the soonest date an
Q58: The amount of time that must separate
Q59: The Gantt chart:
A) is usually difficult to
Q60: _ is the difference between the finish
Q61: Describe the Gantt chart.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents