The additional time added to the schedule that can be used if a scheduled activity exceeds its estimated duration is called _____.
A) lag time
B) lead time
C) contingency time
D) forward pass
E) free float
Correct Answer:
Verified
Q39: The _ schedule is a summary level
Q40: The relationship between a predecessor activity and
Q41: Lead time is _.
A) the amount of
Q42: The time an activity that is not
Q43: An updated schedule that shows the present
Q45: Distributing the work load to reduce uneven
Q46: If activities must begin at the same
Q47: The _ is the sequence of activities
Q48: A sequence that can be determined logically
Q49: Which of the following types of software