All of the following steps, as paraphrased by Tom Mochal, have the necessary components of a change documentation process EXCEPT:
A) inform project stakeholders of the change request process.
B) require that the change request be made in writing.
C) estimate the time needed to evaluate the change.
D) evaluate the change and its impact on the schedule.
E) withhold the distribution of the scope change log to team members .
Correct Answer:
Verified
Q41: The transition from planning to project initiation
Q42: During the start-up phase, a project manager
Q43: Which of the following statements is true
Q44: Roles:
A) are defined as the project progresses.
B)
Q45: Why are changes to the project scope
Q47: Role clarification facilitates the development of all
Q48: The project _ team is responsible for
Q49: _ are those persons in the organization
Q50: A purpose statement:
A) is developed as part
Q51: The types of goals and the processes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents