A disadvantage of having clients actively participate on a project is:
A) that they do not have the project management experience of the project team.
B) that they might decrease their personal investment in the project.
C) that they rarely add value to team discussions and activities.
D) that they may have undue influence on project decisions.
E) that they may conduct full-day meetings for reviews of complex projects.
Correct Answer:
Verified
Q24: Which of the following statements is true
Q25: Which of the following statements is NOT
Q26: On projects with a low complexity level,
Q27: Which of the following will increase the
Q28: By educating the client about the project
Q30: _ is characterized by impartiality and honesty
Q31: Less obvious client expectations about a project
Q32: Which of the following statements is NOT
Q33: Which of the following statements is true
Q34: The client may experience cognitive dissonance, if
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents